Construction of the “Entre Tille et Venelle” wind farm slowed down during the nesting period(12 April 2019)

windfarm nesting period - Velocita

In accordance with the commitments made by Velocita Energies, the construction schedule for the “Entre Tille et Venelle” wind farm was adjusted to protect the nesting species that populate the area around the construction site during their nesting period (April to July).

Velocita made sure that the main civil engineering works (creation of the accesses and foundations) were completed before this period. Only finishing work, the transport of components and the assembly of the first sections of the masts, which are work stages that cause little disturbance to the birds, took place during the nesting period.